Prevoius Weekly Reports

   weekly progress 18.2.2011
    

RBDCK, Manager in Charge JemyMathew Contact No9447078783

KITCO,Consultant,Engineer in charge  Santhosh G- Contact no 9447384217

CVCC,Contractor ,Engineer in charge Shaji-Contact No9747004340 

 

 

SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week (1) Balance  work (2) Cumulative delay in weeks after  suuplly agmnt(3) Work  planned  during the week(4)  Actual work done during the last week (5) Short fall in the last week  (6) Work Planned for next week  (7)   Remarks 
             
             
1 Re wall towards NH side  100% 2% 98 18 0 0 0 0   
2 RE wall towards Pulikkakadavuside  100% 99 2 38 1 1 1   
3 Approach  5 No  4 1 27   
 Span 
4 Railway  3No  0 0 25               
 span 
5 Pile (Rly)pulikakadavu side  9 4 5 45  0  0   0    0   caution awaited
  
6 Pile (Rly)Nh side  9 3 6   1 1 0 1 railways Signal cable to be shifted
6 Piers (Rly)  4No  0 0 35               
7    426m  390 36     60  40  20   36    
Handrail  
(in the pulikkakadavu side) 
  
8 Kerb  639m  490 149  70   40  30  100     

 

DATE 12/2/2011 14/2/2011  15/2/2011  16/2/2011  17/2/2011  18/2/2011 
Weather  Sunny  Sunny  Sunny  Sunny  Sunny  Sunny 
No of labours 55 56 57 61 57 60 
 
Back
 
    
WORK OF RE WALL PORTION ON NH SIDE 17.2.2011

    
    
WORK OF RE WALL ON NH SIDE IS IN PROGRESS 18.2.2011

    
    
WORK OF HAND RAIL PORTION COMPLETED 12.2.2011

    
    
REINFORCEMENT FOR PILE CAP AT P2 ON PULIKKAKADAVU SIDE 15.2.2011

    
 
    
REINFORCEMENT FOR PILE CAP AT P2 ON PULIKKAKADAVU SIDE 17.2.2011

    
    
PILING WORK IN PROGRESS ON NH SIDE 17.2.2011

    
    
PILE CONCRETING AT P1 ON NH SIDE 12.2.2011

    
 
    
PCC FOR PILE CAP AT P2 12.2.2011

      
 

 

 

 

 

 

 

 