SI.No |
Particulars |
|
Details |
1 |
Date of Tender Notification |
|
6.1.2010 |
2 |
Date of opening of Tender |
|
27.2.2010 |
|
3 |
Name of the contractor |
|
M/s GPT Infraprojects ltd. |
|
4 |
Letter of Acceptance |
|
23.4.2010 |
5 |
Date of agreement |
|
9.6.2010 |
6 |
Notice to proceed issued |
|
21.6.2010 |
7 |
Expected date of completion as per the original agreement |
|
31.3.2012 |
8 |
Contract amount - PAC (Rs) |
|
8,36,96,738.00
|
9 |
Adjacent span - date of tender |
|
31.12.2012 |
10 |
Letter of acceptance |
|
23.02.2013 |
11 |
Contract PAC of the adjacent span (Rs) |
|
92,34,033.00 |
12 |
Name of the contractor |
|
M/s RDS Projects Ltd |
13 |
Date of agreement |
|
13.03.2013 |
14 |
Notice to proceed |
|
14.06.2013 |
15 |
Actual date of completion |
|
13.10.2013 |
16 |
LA cost (Rs) |
|
26,01,613.00 |
17 |
utility shifting and consultancy charges |
|
64,41,122.00 |
|
Total cost of the project excluding interest of term loan (Rs) [SL No. 8+11+16+17] |
|
10,19,73,506 |
18 |
LC. No |
|
216 |
19 |
Location |
|
Rly km 714/4 Between Badagara and Mukali Station |
20 |
Project Management Consultant and supervision |
|
Mr Baiju John, M/s Kerala Industrial Technical Consultancy Organization Ltd,Kochi. |
21 |
Length of structure(m) |
|
443.5 |
22 |
Present status of work |
|
All works have been completed and the bridge is open to traffic from 05.07.2014.
|
|