ROB at Kainatty
 
SI.No Particulars   Details
1 Date of Tender Notification   6.1.2010
2 Date of opening of Tender   27.2.2010  
3 Name of the contractor    M/s GPT Infraprojects ltd.  
4 Letter of Acceptance   23.4.2010
5 Date of agreement   9.6.2010
6 Notice to proceed issued   21.6.2010
7 Expected date of completion as per the original agreement   31.3.2012
8 Contract amount - PAC (Rs)  

8,36,96,738.00

9 Adjacent span - date of tender    31.12.2012
10 Letter of acceptance   23.02.2013
11 Contract PAC of the adjacent span (Rs)   92,34,033.00
12 Name of the contractor   M/s RDS Projects Ltd
13 Date of agreement   13.03.2013
14 Notice to proceed   14.06.2013
15 Actual date of completion   13.10.2013
16 LA cost (Rs)   26,01,613.00
17 utility shifting and consultancy charges   64,41,122.00
  Total cost of the project excluding interest of term loan (Rs) [SL No. 8+11+16+17]   10,19,73,506
18 LC. No   216
19 Location   Rly km 714/4 Between Badagara and Mukali Station
20 Project Management Consultant and supervision   Mr Baiju John, M/s Kerala Industrial Technical Consultancy Organization Ltd,Kochi.
21 Length of structure(m)   443.5
22 Present status of work  

All works have been completed and the bridge is open to traffic from 05.07.2014.

 

 

 

 

 

 

 

 

 

 

 