   Weekly Progress for Rob Eroor 07.02.2017 to 15.02.2017
    
Sl No. Item Description Estimated Qty Executed Qty Upto Previous Week Works During Week Executed Qty Upto Present Week Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
4 PIERCAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A2,P5  
5 RETAINING WALL 294 294 0 0 294 0 Completed  
6 VOID SLAB 8 8 0 0 8 0 A1-P1,P1-P2,P2-P3,       P3-P4,A2-P8,P7-P8,          P5-P6,P6-P7  
7 VOID SLAB ADJ. 2 2 0 0 2 0 RP1-P4,RP2-P5  
8 EXPANSION JOINT 8 0 0 0 8 0 Started  
9 HANDRAILS 1100 Nos 1100 30 30 1100 0 Completed  
10 KERB 1100 Nos 1100 0 0 1100 0 Completed  
11 ROAD WORK M 100 0% 0% 100% 0 BC Completed  
12 DRAINAGE M 450 0 0 450   Completed  
13 HANDRAIL FIXING 666 M 641 0 0 666 0 Completed  
14 KERB FIXING Spans 10 0 0 10 0 Completed  
15 APPROACH Nos              
  Palarivattom End   1 0% 0% 100% 0 BC Completed  
  Tripunithura End   1 0% 0% 100% 0 BC Completed  
16 Staircase                
  Palarivattom End             In progress ( Completed upto 2nd flight )  
  Tripunithura End             Not started  
17 DRAINAGE Palarivattom End 165 m              1) 45 mtr Drainage completed ,               2) RCC raft done         ( from 45 m to 85 mtr)  
18 Road Kerb Fixing 270 m 225 0 0 225 0    
19 Paver Tile under spans                
  Tripunithura Side             Started Materials arranged at site
 
Back