Weekly progress report of Eroor ROB as on 040217 |
1. Construction of stair case is progressing at Palarivattom side. Completed upto 1st Flight columns.
2. Drainage work at Palarivattom side is progressing.
3. Laying of paver block in walkway (under the spans ) are started.
| |