Prevoius Weekly Reports

   Progress RBDCK January 2017
    
Sl No. Item Description Estimated Qty Executed Qty Upto December 2016 Works During January Executed Qty Upto January Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
4 PIERCAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A2,P5  
5 RETAINING WALL 294 294 0 0 294 0 Completed  
6 VOID SLAB 8 8 0 0 8 0 A1-P1,P1-P2,P2-P3,       P3-P4,A2-P8,P7-P8,          P5-P6,P6-P7  
7 VOID SLAB ADJ. 2 2 0 0 2 0 RP1-P4,RP2-P5  
8 EXPANSION JOINT 8 0 0 0 8 0 Started  
9 HANDRAILS 1100 Nos 1100 30 30 1100 0 Completed  
10 KERB 1100 Nos 1100 0 0 1100 0 Completed  
11 ROAD WORK M 100 0% 0% 100% 0 BC Completed  
12 DRAINAGE M 450 0 0 450   Completed  
13 HANDRAIL FIXING 666 M 641 25 25 666 0 Completed  
14 KERB FIXING Spans 10 0 0 10 0 Completed  
15 APPROACH Nos              
  Palarivattom End   1 100% 100% 100% 0 BC Completed  
  Tripunithura End   1 100% 100% 100% 0 BC Completed  
16 Staircase                
  Palarivattom End             In progress ( Completed upto Grade Beam)  
  Tripunithura End             Not started  
17 DRAINAGE Palarivattom End 165 m           IN progress (Completed upto 40 m )  
18 Road Kerb Fixing 270 m 225 0 0 225 45    
19 Paver Tile under spans                
  Tripunithura Side             Not started Materials arranged at site
 
Back
 
    
STAIRCASE WORK AT PALARIVATTOM SIDE

    
    
IMAGE 3

    
    
FULLSIZERENDER

    
    
DRAIN ALONG PALARIVATTOM SERVICE ROAD

    
 
 
 

 

 

 

 

 

 

 