Name of Work |
DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR |
Name of Contractor |
M/S SKILLED CONSTRUCTION COMPANY LTD |
Work Order No. |
RBDC/WORKS/05/2014 |
Work Order Value (Rs) |
1145,75,251 |
Date of commencement |
01.12.2014 |
Date of completion (agreement) |
31.05.2016 |
Date of completion (extended) |
In Progress |
Date of submission |
29.11.2016 |
|
|
|
|
|
|
|
|
|
Sl No. |
Item Description |
Estimated Qty |
Executed Qty Upto October 2016 |
Works During October |
Executed Qty Upto November |
Balance Qty |
Details of completed items. |
Planned |
Executed |
1 |
PILE |
38 |
38 |
0 |
0 |
38 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
2 |
PILECAP |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
3 |
PIER |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
4 |
PIERCAP |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P6,P7,P8,A2,P5 |
5 |
RETAINING WALL |
294 |
294 |
|
0 |
294 |
0 |
Completed |
6 |
VOID SLAB |
8 |
8 |
0 |
0 |
8 |
0 |
A1-P1,P1-P2,P2-P3, P3-P4,A2-P8,P7-P8, P5-P6,P6-P7 |
7 |
VOID SLAB ADJ. |
2 |
2 |
0 |
0 |
2 |
0 |
RP1-P4,RP2-P5 |
8 |
EXPANSION JOINT |
8 |
0 |
0 |
0 |
0 |
8 |
Started |
9 |
HANDRAILS |
1100 Nos |
1070 |
30 |
30 |
1100 |
0 |
|
10 |
KERB |
1100 Nos |
1100 |
0 |
0 |
1100 |
0 |
Completed |
11 |
ROAD WORK |
M |
350 |
100% |
100% |
100% |
0 |
BC Completed |
12 |
DRAINAGE |
M |
428 |
22 |
22 |
450 |
|
|
13 |
HANDRAIL FIXING |
666 M |
528 |
138 |
113 |
641 |
25 |
|
14 |
KERB FIXING |
Spans |
10 |
3 |
3 |
13 |
0 |
|
15 |
APPROACH |
Nos |
2 |
|
|
|
|
|
|
Palarivattom End |
|
1 |
100% |
100% |
100% |
|
BC Completed |
|
Tripunithura End |
|
1 |
100% |
100% |
100% |
|
BC Completed |
|