   Progress report of Eroor ROB - 29.11-16
    
Name of Work  DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR
Name of Contractor M/S SKILLED CONSTRUCTION COMPANY LTD
Work Order No. RBDC/WORKS/05/2014
Work Order Value (Rs) 1145,75,251
Date of commencement 01.12.2014
Date of completion (agreement) 31.05.2016
Date of completion (extended) In Progress
Date of submission 29.11.2016
                 
Sl No. Item Description Estimated Qty Executed Qty Upto October 2016 Works During October Executed Qty Upto November Balance Qty Details of completed items.
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2
4 PIERCAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A2,P5
5 RETAINING WALL 294 294   0 294 0 Completed
6 VOID SLAB 8 8 0 0 8 0 A1-P1,P1-P2,P2-P3,       P3-P4,A2-P8,P7-P8,          P5-P6,P6-P7
7 VOID SLAB ADJ. 2 2 0 0 2 0 RP1-P4,RP2-P5
8 EXPANSION JOINT 8 0 0 0 0 8 Started
9 HANDRAILS 1100 Nos 1070 30 30 1100 0  
10 KERB 1100 Nos 1100 0 0 1100 0 Completed
11 ROAD WORK M 350 100% 100% 100% 0 BC Completed
12 DRAINAGE M 428 22 22 450    
13 HANDRAIL FIXING 666 M 528 138 113 641 25  
14 KERB FIXING Spans 10 3 3 13 0  
15 APPROACH Nos 2          
  Palarivattom End   1 100% 100% 100%   BC Completed
  Tripunithura End   1 100% 100% 100%   BC Completed
 