MONTHLY PROGRESS REPORT FOR THE MONTH OF OCTOBER 2016 |
|
|
Name of Work |
DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR |
|
|
Name of Contractor |
M/S SKILLED CONSTRUCTION COMPANY LTD |
|
|
Work Order No. |
RBDC/WORKS/05/2014 |
|
|
Work Order Value (Rs) |
1145,75,251 |
|
|
Date of commencement |
01.12.2014 |
|
|
Date of completion (agreement) |
31.05.2016 |
|
|
Date of completion (extended) |
In Progress |
|
|
Name of Site Engineer |
GEORGE THAMBI |
|
|
Date of submission |
29.10.2016 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sl No. |
Item Description |
Estimated Qty |
Executed Qty Upto September 2016 |
Works During October |
Executed Qty Upto October |
Balance Qty |
Details of completed items. |
Remarks |
|
|
Planned |
Executed |
|
|
1 |
PILE |
38 |
38 |
0 |
0 |
38 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
|
|
|
2 |
PILECAP |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
|
|
|
3 |
PIER |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
|
|
|
4 |
PIERCAP |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P6,P7,P8,A2,P5 |
|
|
|
5 |
RETAINING WALL |
294 |
294 |
|
0 |
294 |
0 |
COMPLETED |
|
|
|
6 |
VOID SLAB |
8 |
8 |
0 |
0 |
8 |
0 |
A1-P1,P1-P2,P2-P3, P3-P4,A2-P8,P7-P8, P5-P6,P6-P7 |
|
|
|
7 |
VOID SLAB ADJ. |
2 |
1 |
1 |
1 |
2 |
0 |
P4-RP1 |
|
|
|
8 |
EXPANSION JOINT |
8 |
0 |
0 |
0 |
0 |
8 |
|
|
|
|
9 |
HANDRAILS |
1100 Nos |
1020 |
50 |
50 |
1070 |
30 |
|
|
|
|
10 |
KERB |
1100 Nos |
1070 |
30 |
30 |
1100 |
0 |
|
|
|
|
11 |
ROAD WORK |
M |
350 |
0 |
0 |
350 |
|
Completed upto WMM |
|
|
|
12 |
DRAINAGE |
M |
398 |
30 |
30 |
428 |
|
|
|
|
|
13 |
HANDRAIL FIXING |
666 M |
494 |
34 |
34 |
528 |
138 |
|
|
|
|
14 |
KERB FIXING |
Spans |
7 |
3 |
3 |
10 |
0 |
|
|
|
|
15 |
APPROACH |
|
2 |
2 |
2 |
2 |
0 |
|
|
|
|
|
Palarivattom End |
|
|
|
|
|
|
WMM Completed |
|
|
|
|
Tripunithura End |
|
|
|
|
|
|
WMM Completed |
|
|
|
|