   Progress report of Eroor ROB-04.10.2016
    
Name of Work  DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR
Name of Contractor M/S SKILLED CONSTRUCTION COMPANY LTD
Work Order No. RBDC/WORKS/05/2014
Work Order Value (Rs) 1145,75,251
Date of commencement 01.12.2014
Date of submission 04.10.2016
                   
Sl No. Item Description Estimated Qty Executed Qty Upto August 2016 Works During September Executed Qty Upto September Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
4 PIERCAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A2,P5  
5 RETAINING WALL 294 294 (100% PVTM side and 100 % Tripunithura side) 0 294 0 COMPLETED  
6 VOID SLAB 8 8 0 0 8 0 A1-P1,P1-P2,P2-P3,       P3-P4,A2-P8,P7-P8,          P5-P6,P6-P7  
7 VOID SLAB ADJ. 2 1 1 1 2 0 P4-RP1  
8 EXPANSION JOINT 10 0 0 0 0 10    
9 HANDRAILS 1100 Nos 828 0 192 1020 80    
10 KERB 1100 Nos 1032 0 38 1070 30    
11 ROAD WORK M 350 0 0 350   Completed upto WMM  
12 DRAINAGE M 398 40 0 398      
13 HANDRAIL FIXING 666 M 338 0 156 494 172    
14 KERB FIXING Spans 5 5 2 7 3    
15 APPROACH                
  Palarivattom End             WMM Completed  
  Tripunithura End             WMM Completed  
 