   Weekly Progress report as on 11/02/2011
    

   

Progress Report For Kainatty ROB for the week ending on 11-02-2011
Si No
Activity Description
Total Quantity
Cumulative progress upto last week
Balance  work up to last week
Cumulative delay in Qty up to last week
Work  planned  during the week
Actual work done during the week
Cumulative delay in Qty up to this week
Work  Planned for next week
Remarks
1
PILE KAINATTY  SIDE
18
18
0
0
0
0
0
0
 
2
PILE NADAPURAM SIDE
27
19
8
5
4
5
0
3
 
3
PILE CAP KAINATTY SIDE
6
0
6
6
4
0
6
4
 
4
PILE CAP  NADAPURAM SIDE
9
2
7
4
3
2
3
3
 
5
PIER KAINATTY  SIDE
6
0
6
5
3
0
6
3
 
6
PIER NADAPURAM SIDE
9
0
9
2
2
0.5
1.5
2
 
7
PIER CAP KAINATTY  SIDE
6
0
6
3
2
0
4
3
 
8
PIER CAP NADAPURAM SIDE
9
0
9
2
2
0
2
3
 
 
Back
 
    
PILE CAP P8 (09/02/2011)

    
    
CONCRETING OF PILE P13 A (08/02/2011)

    
    
STAGING MATERIALS (09/02/2011)

    
    
3 BAG MIXER MACHINE (09/02/2011)

    
 
    
PIER P7 (08/02/2011)

    
    
SPRINKLING OF WATER ON DIVERSION ROAD (06/02/2011)

      
 

 

 

 

 

 

 

 