Name of Work |
DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR |
Name of Contractor |
M/S SKILLED CONSTRUCTION COMPANY LTD |
Work Order No. |
RBDC/WORKS/05/2014 |
Work Order Value (Rs) |
1145,75,251 |
Date of commencement |
01.12.2014 |
Date of completion (agreement) |
31.05.2016 |
Date of completion (extended) |
In Progress |
|
|
|
|
|
|
|
|
|
|
Sl No. |
Item Description |
Estimated Qty |
Executed Qty Upto June 2016 |
Works During July |
Executed Qty Upto July |
Balance Qty |
Details of completed items. |
Remarks |
Planned |
Executed |
1 |
PILE |
38 |
38 |
0 |
0 |
38 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
|
2 |
PILECAP |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
|
3 |
PIER |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P5,P6,P7,P8,A2 |
|
4 |
PIERCAP |
10 |
10 |
0 |
0 |
10 |
0 |
A1,P1,P2,P3,P4,P6,P7,P8,A2,P5 |
|
5 |
RETAINING WALL |
294 |
250 |
(100% PVTM side and 100 % Tripunithura side) |
10 |
260 |
34 |
|
|
6 |
VOID SLAB |
8 |
8 |
0 |
0 |
8 |
0 |
A1-P1,P1-P2,P2-P3, P3-P4,A2-P8,P7-P8, P5-P6,P6-P7 |
|
7 |
VOID SLAB ADJ. |
2 |
1 |
0 |
0 |
1 |
1 |
RP2-P5 |
|
8 |
EXPANSION JOINT |
10 |
0 |
0 |
0 |
0 |
10 |
|
|
9 |
HANDRAILS |
1100 Nos |
768 |
0 |
0 |
768 |
332 |
|
|
10 |
KERB |
1100 Nos |
960 |
0 |
0 |
960 |
140 |
|
|
11 |
ROAD WORK |
M |
100 |
250 |
250 |
350 |
|
Completed upto WMM |
|
12 |
DRAINAGE |
M |
336 |
30 |
32 |
368 |
|
|
|
13 |
HANDRAIL FIXING |
666 M |
338 |
0 |
0 |
338 |
328 |
|
|
|