Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886929
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Progress report of Eroor ROB-31.07.2016
    
Name of Work  DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR
Name of Contractor M/S SKILLED CONSTRUCTION COMPANY LTD
Work Order No. RBDC/WORKS/05/2014
Work Order Value (Rs) 1145,75,251
Date of commencement 01.12.2014
Date of completion (agreement) 31.05.2016
Date of completion (extended) In Progress
                   
Sl No. Item Description Estimated Qty Executed Qty Upto June 2016 Works During July Executed Qty Upto July Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
4 PIERCAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A2,P5  
5 RETAINING WALL 294 250 (100% PVTM side and 100 % Tripunithura side) 10 260 34    
6 VOID SLAB 8 8 0 0 8 0 A1-P1,P1-P2,P2-P3,       P3-P4,A2-P8,P7-P8,          P5-P6,P6-P7  
7 VOID SLAB ADJ. 2 1 0 0 1 1 RP2-P5  
8 EXPANSION JOINT 10 0 0 0 0 10    
9 HANDRAILS 1100 Nos 768 0 0 768 332    
10 KERB 1100 Nos 960 0 0 960 140    
11 ROAD WORK M 100 250 250 350   Completed upto WMM  
12 DRAINAGE M 336 30 32 368      
13 HANDRAIL FIXING 666 M 338 0 0 338 328    
 
Back
 
    
REINFORCEMENT WORK FOR RETAINING WALL

    
    
RETAINING WALL RAFT PALARIVATTOM END

    
    
PICTURE3

    
    
PICTURE1

    
 
    
PICTURE2

      
 

 

 

 

 

 

 

 