   Weekly report as on 11.02.2011
    

 

 

Progress Report For MulankunnathukavuROB for the week ending on 11-02-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE SHORNUR  SIDE

9

9

0

0

0

0

0

0

 

2

PILE M.C SIDE

36

36

0

0

0

0

0

0

 

3

PILE CAP SHORNUR SIDE

3

3

0

0

0

0

0

0

 

4

PILE CAP  M.C SIDE

12

12

0

0

0

0

0

0

 

5

PIER SHORNUR  SIDE

3

3

0

0

0

0

0

0

 

6

PIER M.C SIDE

12

12

0

0

0

0

0

0

 

7

PIER CAP SHORNUR  SIDE

3

0

3

2

2

3

0

0*

*Pedastal concreting

8

PIER CAP M.C SIDE

12

12

0

0

0

0

0

0

*Pedastalconcreting

 