   Progress report of Eroor ROB-31.05.16
    
Name of Work  DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR
Name of Contractor M/S SKILLED CONSTRUCTION COMPANY LTD
Work Order No. RBDC/WORKS/05/2014
Work Order Value (Rs) 1145,75,251
Date of commencement 01.12.2014
                   
Sl No. Item Description Estimated Qty Executed Qty Upto March 2016 Works During April Executed Qty Upto April Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
4 PIERCAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A2,P5  
5 RETAINING WALL 294 210 100% PVTM side 40 250 44    
6 VOID SLAB 8 8 0 0 8 0 A1-P1,P1-P2,P2-P3,       P3-P4,A2-P8,P7-P8,          P5-P6,P6-P7  
7 VOID SLAB ADJ. 2 0 1 1 0 1 RP2-P5  
8 EXPANSION JOINT 10 0 0 0 0 10    
9 HANDRAILS 1100 Nos 768 100 100 868 232    
10 KERB 1100 Nos 960 100 0 960 140    
11 ROAD WORK M 0 100 0 100      
12 DRAINAGE M 0 60 50 270      
13 HANDRAIL FIXING 666 M 152 120 120 272 394    
 
Back
 
    
PAINTING WORK-PVTM SIDE

    
    
RETAINING WALL - TPRA SIDE

    
    
HANDRAIL FIXING - TPRA SIDE

    
    
DESHUTTERING RP2-P5

    
 
 
 

 

 

 

 

 

 

 