   weekly progress as on 11.2.2011
    

RBDCK, Manager in Charge JemyMathew Contact No9447078783

KITCO,Consultant,Engineer in charge  Santhosh G- Contact no 9447384217

CVCC,Contractor ,Engineer in charge Shaji-Contact No9747004340

SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week 1 Balance  work (2) Cumulative delay in weeks after suuple agmnt(3) Work  planned  during the week (4) Actual work done during the last week (5) Short fall in the last week  (6) Work  planned for next week  Remarks 
             
             
1 Re wall towards NH side  100% 2% 98 18 0 0 0 0   
2 RE wall towards Pulikkakadavuside  100% 99 2 38 1 1 1   
3 Approach  5 No  4 1 27   
 Span 
4 Railway  3No  0 0 25               
 span 
5 Pile (Rly)pulikakadavu side  9 4 5 45  2  0 2  0  caution awaited 
  
6 Pile (Rly)Nh side  9 3     2 2 0 1 Railways Signal cable to be removed 
6 Piers (Rly)  4No  0 0 35               
7    426m  350 76     60  60  -   76    
Handrail  
(in the pulikkakadavu side) 
  
8 Kerb  639m  450 189  70   70   100    

 

DATE 5/2/2011 7/2/2011 8/2/2011 9/2/2011 10/2/2011 11/2/2011
Weather  Sunny  Sunny  Sunny  Sunny Sunny  Sunny 
No.of labours 56 55 56 60 58 60 
 
Back
 
    
WORK OF HAND RAIL IS IN PROGRESS 11.2.2011

    
    
WORK OF KERB 10.2.2011

    
    
WORK OF HAND RAIL IS IN PROGRESS 10.2.2011

    
    
WORK OF HAND RAIL IS IN PROGRESS 9.2.2011

    
 
    
PILE CONCRETING ON NH SIDE 05.2.2011

      
 

 

 

 

 

 

 

 