   Progress report of Eroor ROB-30.04.16
    

Date of commencement 01.12.2014
Date of completion (agreement) 31.05.2016
Date of submission 30.04.2016
                   
Sl No. Item Description Estimated Qty Executed Qty Upto March 2016 Works During April Executed Qty Upto March Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
4 PIERCAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A2,P5  
5 RETAINING WALL 312 210 100% PVTM side
90% Thripunithura
15 225 87    
6 VOID SLAB 8 8 0 0 8 0 A1-P1,P1-P2,P2-P3, P3-P4,A2-P8,P7-P8, P5-P6,P6-P7  
7 VOID SLAB ADJ. 2 0 2 1 1 2 P5-RP2  
8 EXPANSION JOINT 10 0 0 0 0 10    
9 HANDRAILS 1100 Nos 768 400 0 768 332    
10 KERB 1100 Nos 960 400 0 960 140    
11 ROAD WORK M 100 100 0 100      
12 DRAINAGE M 0 60 10 270      
13 HANDRAIL FIXING 666 M 152 152 0 152 514    
 
Back
 
    

    
    
EROOR ROB-30.04.16

    
    
EROOR ROB-30.04.16

    
    
EROOR ROB-30.04.16

    
 
    
PROGRESS GRAPH OF EROOR ROB-30.04.16

      
 

 

 

 

 

 

 

 