   Progress report of Eroor ROB-02.04.16
    
Name of Work  DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR
Name of Contractor M/S SKILLED CONSTRUCTION COMPANY LTD
Work Order No. RBDC/WORKS/05/2014
Work Order Value (Rs) 1145,75,251
Date of commencement 01.12.2014
Date of completion (agreement) 31.05.2016
                   
Sl No. Item Description Estimated Qty Executed Qty Upto February 2016 Works During March Executed Qty Upto March Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
4 PIERCAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A2,P5  
5 RETAINING WALL 312 190 100% PVTM side 20 210 102    
6 VOID SLAB 8 8 0 0 8 0 A1-P1,P1-P2,P2-P3,       P3-P4,A2-P8,P7-P8,          P5-P6,P6-P7  
7 VOID SLAB ADJ. 2 0 0 0 0 2    
8 EXPANSION JOINT 10 0 0 0 0 10    
9 HANDRAILS 1100 Nos 668 400 100 768 332    
10 KERB 1100 Nos 810 400 150 960 140    
11 ROAD WORK M 0 100 100 100      
12 DRAINAGE M 0 60 50 270      
13 HANDRAIL FIXING 666 M 0 152 152 152 514    
 
Back
 
    
RWALL WORK AT PALARIVATTAM SIDE

    
    
RWALL EXCAVATION AT TRIPUNITHURA SIDE

    
    
DRAINAGE PALARIVATTAM SIDE

    
    
ADJACENT SPAN (RP2-P5) STAGING WORK -TRIPUNITHURA SIDE

    
 
 
 

 

 

 

 

 

 

 