   Progress report of Eroor ROB-29.02.2016
    
Sl No. Item Description Estimated Qty Executed Qty Upto January 2016 Works During February Executed Qty Upto February Balance Qty
Planned Executed
1 PILE 38 38 0 0 38 0
2 PILECAP 10 10 0 0 10 0
3 PIER 10 10 0 0 10 0
4 PIERCAP 10 10 0 0 10 0
5 RETAINING WALL 312 146 100 20 166 146
6 VOID SLAB 8 8 0 0 8 0
7 VOID SLAB ADJ. 2 0 0 0 0 2
8 EXPANSION JOINT 10 0 0 0 0 10
9 HANDRAILS 1100 Nos 565 400 0 565 535
10 KERB 1100 Nos 648 400 162 810 290
11 ROAD WORK M 0 100 100 100  
12 DRAINAGE M 0 0 0 220  
13 HANDRAIL FIXING 666 M 0 152 152 152 514
 