   Progress report of Angadipuram ROB-20.02.16
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 Pile 56 56 0 0 0 0 0 0
2 Pilecap 18 18 0 0 0 0 0 0
3 Pier 18 18 0 0 0 0 0 0
4 Piercap 16 16 0 0 0 0 0 0
5 Girders(span) 18 17 1 0 1 1 0 6
6 Deckslab 18 16 2 0 0 0 0 1
7 Expansion joint 20 16 4 0 0 0 0 0
8 Handrail-Bridge portion 18 18 0 0 0 0 0 0
9 Handrail-Approach portion 100% 100% 0% 0 0 0 0 0
10 Retaining wall-Perinthalmanna side-RHS 100% 100% 0% 0% 0% 0% 0% 0%
11 Retaining wall-Perinthalmanna side-LHS 100% 100% 0% 0% 0% 0% 0% 0%
12 Retaining wall-Angadipuram side-RHS 100% 100% 0% 0% 0% 0% 0% 0%
13 Retaining wall-Angadipuram side-LHS 100% 100% 0% 0% 0% 0% 0% 0%
14 Earth filling at Perinthalmanna and Angdipuram side 100% 100% 0% 0% 0% 0% 0% 0%
15 GSB & WMM Angadipuram side 100% 0% 100% 0% 100% 100% 0% 0%
16 GSB & WMM Perinthalmanna sideside 100% 0% 100% 0% 0% 0% 0% 100%
17 Painting 100% 30% 70% 0% 30% 30% 0% 40%
18 service Road -Angadipuram side-LHS(Full length) 100% 80% 20% 0% 0% 0% 0% 0%
19 service Road -Angadipuram side-RHS(Full length) 100% 75% 25% 0% 0% 0% 0% 0%
20 service Road -Perinthalmanna side-LHS(Full length) 100% 50% 50% 0% 0% 0% 0% 0%
21 service Road -Perinthalmanna side-RHS(Full length) 100% 95% 5% 0% 0% 0% 0% 0%
                   
                   
                   
                   
  Availbility of Men                 
  Date 14-02-2016 15-02-2016 16-02-2016 17-02-2016 18-02-2016 19-02-2016 20-02-2016  
  No of labours 77 76 78 83 75 75 75  
 