Sl.No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
1 |
Pile |
56 |
56 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
Pilecap |
18 |
18 |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
Pier |
18 |
18 |
0 |
0 |
0 |
0 |
0 |
0 |
4 |
Piercap |
16 |
16 |
0 |
0 |
0 |
0 |
0 |
0 |
5 |
Girders(span) |
18 |
16 |
2 |
0 |
0 |
0 |
0 |
0 |
6 |
Deckslab |
18 |
16 |
2 |
0 |
0 |
0 |
0 |
0 |
|
Expansion joint |
16 |
6 |
10 |
0 |
6 |
1 |
5 |
9 |
|
Handrail-Bridge portion |
18 |
100 |
9 |
0 |
5 |
3 |
2 |
4 |
|
Handrail-Approach portion |
100% |
0 |
100% |
0 |
0 |
0 |
0 |
0 |
7 |
Retaining wall-Perinthalmanna side-RHS |
100% |
100% |
0% |
0% |
0% |
0% |
0% |
0% |
8 |
Retaining wall-Perinthalmanna side-LHS |
100% |
80% |
20% |
0% |
20% |
20% |
0% |
0% |
9 |
Retaining wall-Angadipuram side-RHS |
100% |
70% |
30% |
0% |
30% |
30% |
0% |
0% |
10 |
Retaining wall-Angadipuram side-LHS |
100% |
100% |
0% |
0% |
0% |
0% |
0% |
0% |
11 |
service Road -Angadipuram side-LHS(Full length) |
100% |
80% |
20% |
0% |
0% |
0% |
0% |
0% |
12 |
service Road -Angadipuram side-RHS(Full length) |
100% |
75% |
25% |
0% |
0% |
0% |
0% |
0% |
13 |
service Road -Perinthalmanna side-LHS(Full length) |
100% |
50% |
50% |
0% |
0% |
0% |
0% |
0% |
14 |
service Road -Perinthalmanna side-RHS(Full length) |
100% |
95% |
5% |
0% |
0% |
0% |
0% |
0% |