Prevoius Weekly Reports

   Progress report of Angadipuram ROB-31.12.2015
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 Pile 56 56 0 0 0 0 0 0
2 Pilecap 18 18 0 0 0 0 0 0
3 Pier 18 18 0 0 0 0 0 0
4 Piercap 16 16 0 0 0 0 0 0
5 Girders(span) 18 14 4 0 2 2 0 0
6 Deckslab 18 12 6 0 1 1 0 1
7 Retaining wall-Perinthalmanna side-RHS 100% 100% 0% 0% 0% 0% 0% 0%
8 Retaining wall-Perinthalmanna side-LHS 100% 40% 60% 0% 30% 30% 0% 30%
9 Retaining wall-Angadipuram side-RHS 100% 40% 60% 0% 0% 0% 0% 30%
10 Retaining wall-Angadipuram side-LHS 100% 40% 60% 0% 30% 30% 0% 30%
11 service Road -Angadipuram side- LHS(Full length) 100% 80% 20% 0% 0% 0% 0% 0%
12 service Road -Angadipuram side- RHS(Full length) 100% 75% 25% 0% 0% 0% 0% 0%
13 service Road -Perinthalmanna side- LHS(Full length) 100% 50% 50% 0% 0% 0% 0% 0%
14 service Road -Perinthalmanna side- RHS(Full length) 100% 95% 5% 0% 0% 0% 0% 0%
                   
                   
  Availbility of Men                 
  Date 25-12-2015 26-12-2015 27-12-2015 28-12-2015 29-12-2015 30-12-2015 31-12-2015  
  No of labours 89 92 93 91 90 94 94  
 
Back
 
    
RETAINING-WALL-CONCRETE-PERINTHALMANNA-SIDE

    
    
DECKSLAB P9-P10

    
    
DECKSLAB-P10-P11-CONCRETING

    
    
HANDRAIL-WORK-AT-SPAN-P1-P2-AND-P2-P3

    
 
    
RETAINING-WALL-PERINTHALMANNA-SIDE

    
    
HANDRAIL-HORIZONTAL-POST

    
    
PERINTHALMANNA-SIDE-RETAINING-WALL

    
 
    
GIRDER-P11-P12-TO-P13-P14

    
    
GIRDER-P11-P12-(2)

    
    
DECKSLAB-P10-P11

    
 
 
 

 

 

 

 

 

 

 