Prevoius Weekly Reports

   Progress Report of ROB at Angadipuram for the week ending on 12-12-2015
    
Sl. No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 Pile 56 56 0 0 0 0 0 0
2 Pilecap 18 18 0 0 0 0 0 0
3 Pier 18 17 1 0 1 0 1 1
4 Piercap 16 16 0 0 0 0 0 0
5 Girders(span) 18 11 7 0 1 1 0 1
6 Deckslab 18 9 9 0 1 1 0 1
7 Retaining wall-Perinthalmanna side-RHS 100% 100% 0% 0% 0% 0% 0% 0%
8 Retaining wall-Perinthalmanna side-LHS 100% 100% 100% 0% 0% 0% 0% 25%
9 Retaining wall-Angadipuram side-RHS 100% 100% 100% 0% 10% 10% 0% 25%
10 Retaining wall-Angadipuram side-LHS 100% 100% 100% 0% 0% 0% 0% 20%
11 service Road -Angadipuram side-LHS(Full length) 100% 80% 20% 20% 0% 0% 20% 0%
12 service Road -Angadipuram side-RHS(Full length) 100% 75% 25% 0% 0% 0% 0% 0%
13 service Road -Perinthalmanna side-LHS(Full length) 100% 50% 50% 0% 0% 0% 0% 0%
14 service Road -Perinthalmanna side-RHS(Full length) 100% 95% 5% 0% 0% 0% 5% 5%
                   
                   
  Availbility of Men                 
  Date 06-12-2015 07-12-2015 08-12-2015 09-12-2015 10-12-2015 11-12-2015 12-12-2015  
  No of labours 53 52 51 53 50 50 55  
 
Back
 
    
RETAINING-WALL--ANGADIPURAM-SIDE-RHS

    
    
PILECAP A1

    
    
EARTH-WORK-RETAINING-WALL--PERINTHALMANNA-SIDE-LHS

    
    
EARTH-WORK-RETAINING-WALL--PERINTHALMANNA-SIDE-LHS

    
 
    
GIRDER-P5-P6-STAGING-WORK

    
    
DECKSLAB-CONCRETING-P4-P5

    
    
DECKSLAB P1-P2

    
 
    
DECKSLAB CONCRETING P1-P2

      
 

 

 

 

 

 

 

 