   Progress Report of Eroor Road Over Bridge as on 23.11.15
    
Si No  Activity Description  Total Quantity Cumulative progress upto 23/11/15 Balance  work from 23/11/15 Actual work done during the week Work planned for next week
1 PILE  Palarivattam side 19 19 0 0 0
2 PILE Tripunithura side 19 19 0 0 0
3 PILE CAP Palarivattam side 5 5 0 0 0
4 PILE CAP Tripunithura side 5 5 0 0 0
5 PIER  Palarivattam side 5 5 0 0 0
6 PIER Tripunithura side 5 5 0 0 0
7 PIER CAP Palarivattam side 5 5 0 0 0
8 PIER CAP Tripunithura side 5 5 0 0 0
9 Slab Palarivattam side 4 4 0 0 0
10 Slab Tripunithura side 4 2 2 0 0
11 Adjacent span Palarivattam side 1 0 1 0 0
12 Adjacent span Tripunithura side 1 0 1 0 0
13 Service road Palarivattam east 100% 0% 100% 0% 0%
14 Service road Palarivattam west 100% 0% 100% 0% 0%
15 Service road Tripunithura east 100% 0% 100% 0% 0%
16 Service road Tripunithura west 100% 0% 100% 0% 0%
 