   Weekly Progress of Angadipuram ROB as on 22.11.2015
    


 

 

 

 

Activity Description

Total Qty

Cumulative progress up to last week

Balance work up to last week

Cumulative delay in Qty up to last week

Work planned during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work Planned for next week

1

Pile

56

56

0

0

0

0

0

0

2

Pile cap

18

17

1

0

1

0

1

1

3

Piers & Abutments

18

17

1

0

1

0

1

1

4

Pier cap

16

16

0

0

0

0

0

0

5

Girders (Span)

18

8

10

0

2

1

1

2

6

Deck slab

18

6

12

0

1

1

1

1

7

Retaining wall-Perinthalmanna side RHS

100%

100%

0%

0%

0%

0%

0%

0%

8

Service road-Angadipuram LHS

100%

80%

20%

20%

0%

0%

20%

0%

9

Service road-Angadipuram RHS

100%

75%

25%

0%

0%

0%

0%

0%

10

Service road-Perinthalmanna LHS

100%

50%

50%

0%

0%

0%

0%

0%

11

Service road-Perinthalmanna RHS

100%

95%

5%

0%

0%

0%

5%

5%


 

 
Back
 
    
PHOTOS OF ANGADIPURAM ROB

    
    
PHOTOS OF ANGADIPURAM ROB

    
    
PHOTOS OF ANGADIPURAM ROB

    
    
PHOTOS OF ANGADIPURAM ROB

    
 
    
PHOTOS OF ANGADIPURAM ROB

    
    
PHOTOS OF ANGADIPURAM ROB

    
    
PHOTOS OF ANGADIPURAM ROB

    
 
    
PHOTOS OF ANGADIPURAM ROB

    
    
PHOTOS OF ANGADIPURAM ROB

    
    
PHOTOS OF ANGADIPURAM ROB

    
 
 
 

 

 

 

 

 

 

 

Untitled Document