   Progress Report of Angadipuram ROB-30.10.2015
    

Weekly Progress of Angadipuram ROB as on 30.10.2015

 

 

Activity Description

Total Qty

Cumulative progress up to last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

Pile

56

56

0

0

0

0

0

0

2

Pile cap

18

17

1

0

1

0

1

1

3

Pier/ Abutments

18

17

1

0

1

0

1

1

4

Pier cap

16

15

1

0

1

1

0

0

5

Girders (Span)

18

6

12

0

1

1

0

1

6

Deck slab

18

4

14

0

1

1

0

1

7

Retaining wall-Perinthalmanna side RHS

100%

80%

20%

20%

20%

20%

0%

0%

8

Service road-Angadipuram LHS

100%

80%

20%

20%

20%

0%

20%

20%

9

Service road-Angadipuram RHS

100%

75%

25%

0%

0%

0%

0%

0%

10

Service road-Perinthalmanna LHS

100%

50%

50%

0%

0%

0%

0%

0%

11

Service road-Perinthalmanna RHS

100%

80%

20%

20%

20%

15%

5%

5%

 
Back
 
    
ANGADIPURAM SIDE NEAR P1

    
    
10) RETAINING WALL AND SERVICE ROAD- PERINTHALMANNA SIDE-RHS

    
    
9) RETAINING WALL AND SERVICE ROAD- PERINTHALMANNA SIDE-RHS

    
    
8) GATE SHIFTING WORK

    
 
    
7) GIRDER P13-P14 STAGING WORK

    
    
6) PIERCAP P1

    
    
5) GIRDER P6-P7- WORK IN PROGRESS

    
 
    
4) DECKSLAB P7-P8- WORK IN PROGRESS

    
    
3) DECKSLAB P16-A2

    
    
1) ANGADIPURAM SIDE

    
 
    
2) DECKSLAB P12-P13

      
 

 

 

 

 

 

 

 