Progress report of Kunhippally ROB-30.10.15 | ||||||||||||||||||||||||||||||
ROB at Kunhippalli A. Over all Progress:-Following works are completed as on 31st October 2015 Pile 60/60, Pile load test 1/1, Pile cap 16/16, Pier 16/16, Pier Cap 16/16, Girders 16/16, Deckslab 16/16, RC wall Monthal side 100%, RC wall NH side 40%, Culvert Monthal bridge side 100%, Drain Monthal bridge side 100%, Service road Monthal side 50%, Staircase Monthal side 90%.
B. Progress of Monthly Target for October 2015
.
| |||||||||||||||||||||||||||||||