   Progress report of Eroor ROB-30.10.15
    
MONTHLY PROGRESS REPORT FOR THE MONTH OF  OCTOBER 2015
Name of Work  DESIGN AND CONSTRUCTION OF ROAD OVER BRIDGE AT EROOR
Name of Contractor M/S SKILLED CONSTRUCTION COMPANY LTD
Work Order No. RBDC/WORKS/05/2014
Work Order Value (Rs) 114,575,251
Date of commencement 01.12.2014
Date of completion (agreement) 31.05.2016
Date of completion (extended)  
Date of submission 31.10.2015
 
Sl No. Item Description Estimated Qty Executed Qty Upto September 2015 Works During October Executed Qty Upto October Balance Qty Details of completed items. Remarks
Planned Executed
1 PILE 38 38 0 0 38 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A2  
2 PILECAP 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A3  
3 PIER 10 10 0 0 10 0 A1,P1,P2,P3,P4,P5,P6,P7,P8,A4  
4 PIERCAP 10 9 1 1 10 0 A1,P1,P2,P3,P4,P6,P7,P8,A5.P5  
5 RETAINING WALL 312 17 90 28 45 267    
6 VOID SLAB 8 4 1 1 5 3 A1-P1,P1-P2,P2-P3, P3-P4,A2-P8  
7 VOID SLAB ADJ. 2 0 0 0 0 2    
8 EXPANSION JOINT 10 0 0 0 0 10    
9 HANDRAILS 666 m 0 0 0 0 666 m    
 