   Progress Report of Eroor ROB-09.10.15
    

Weekly Progress of Eroor ROB as on 09.10.15

Sl. No

Activity Description

Total Quantity

Cumulative progress up to 09.10.15

Balance  work up to 09.10.15

Actual work done during the week

Work planned for next week

Remarks

1

PILE  Palarivattom side

19

19

0

0

0

A1-A,B,C / P1-A,B,C,D / P2-A,B,C,D / P3-A,B,C,D / P4-A,B,C,D

2

PILE Tripunithura side

19

19

0

0

0

P5-A,B,C,D / P6-A,B,C,D , P7- A,B,C,D, P8- A,B,C,D, A2-A,B,C

3

PILE CAP Palarivattom side

5

5

0

0

0

A1,P1,P2,P3,P4

4

PILE CAP Tripunithura side

5

5

0

0

0

P5, P6, P7, P8, A2

 

5

PIER  Palarivattom side

5

5

0

0

0

A1,P1,P2,P3,P4

6

PIER Tripunithura side

5

5

0

0

0

A2,P8,P7,P6,P5

7

PIER CAP Palarivattom side

5

5

0

0

0

A1,P1,P2,P3,P4

8

PIER CAP Tripunithura side

5

5

0

0

0

A2,P8,P7,P6,P5

9

Slab Palarivattom side

4

4

0

0

0

P2 - P3, P1-P2,A1-P1,P3-P4

 

10

Slab Tripunithura side

4

0

4

0

0

-

11

Adjacent span Palarivattom side

1

0

1

0

0

-

12

Adjacent span Tripunithura side

1

0

1

0

0

-

13

Service road Palarivattom east

100%

0%

100%

0%

100%

-

14

Service road Palarivattom west

100%

0%

100%

0%

100%

-

15

Service road Tripunithura east

100%

0%

100%

0%

100%

-

16

Service road Tripunithura west

100%

0%

100%

0%

100%

-

 
Back