   Progress report of Divine Nagar ROB-19.09.15
    

Weekly Progress of Adjacent span of Divine Nagar ROB as on 19.09.15

Sl. No:

Particulars

Status

Remarks

1

Slab RP1-P6A ADJACENT SPAN

Completed

 

2

Slab RP2-P7 ADJACENT SPAN

 Completed

 

3

Handrail and kerb

In progress

Kerb completed. Handrail balance at expansion joint area

4

Expansion joint

Completed

 

5

Wearing coat

In progress

 Divine side completed

6

Painting works

In progress

 80% completed

7

Stair case work

In Progress

Footing completed on Divine side. Columns reached up to EGL

 
Back
 
    
RAILWAY PORTION WORKS

    
    
KADUKUTTY SIDE EXCAVATION FOR STAIRCASE

    
    
PAINTING RP1-P6A SPAN.

    
    
RAILWAY SPAN WORK IN PROGRESS.

    
 
    
DIVINE SIDE OF ROB.

    
    
PAINTING WORK IN RP2-P7 SPAN

      
 

 

 

 

 

 

 

 