   Progress Report of Angadipuram ROB-31.08.2015
    

Weekly Progress of Angadipuram ROB as on 31.08.2015

 

 

Activity Description

Total Qty

Cumulative progress up to last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

Pile

56

56

0

0

0

0

0

0

2

Pile cap

18

13

5

3

1

0

3

2

3

Pier/ Abutments

18

11

7

1

2

0

2

2

4

Pier cap

16

9

7

0

0

0

0

2

5

Girders (Span)

18

2

16

1

1

0

1

1

6

Deck slab

18

0

18

1

1

1

0

1

7

Retaining wall

100%

100%

0

0

0

0

0

0

8

Drain

100%

100%

0

0

0

0

0

0

9

Hume pipe laying for road diversion

100%

20%

80%

80%

80%

0

80%

80%

10

Service road-300m

100%

0

100%

100%

100%

70%

30%

30%

 

Date

25/08/2015

26/08/2015

27/08/2015

28/08/2015

29/08/2015

30/08/2015

31/08/2015

No of labours

58

61

62

0

64

63

64

 
Back
 
    
9) COLONY SERVICE ROAD WIDENING-PERINTHALMANNA SIDE

    
    
10) COLONY SERVICE ROAD WIDENING-PERINTHALMANNA SIDE

    
    
7) VIEW FROM DECKSLAB P3-P4

    
    
8) KERB SHUTTERING WORK- SERVICE ROAD ANGADIPURAM SIDE

    
 
    
3) PIERCAP P7 -STAGING WORK

    
    
6) COVERSLAB WORK IN PROGRESS-ANGADIPURAM SIDE

    
    
5) GIDER-P2-P3

    
 
    
4) PIERCAP P8- SHUTTERING WORK

    
    
1) SERVICE ROAD -ANGADIPURAM SIDE

    
    
2) DECKSLAB P3-P4 CONCRETING

    
 
 
 

 

 

 

 

 

 

 