   Progress report of Divine Nagar ROB-26.08.15
    

Weekly Progress of Adjacent span of Divine Nagar ROB as on 26.08.15

Sl. No:

Particulars

Status

Remarks

1

Slab RP1-P6A ADJACENT SPAN

Completed

Slab completed

2

Slab RP2-P7 ADJACENT SPAN

 In progress

Slab completed

3

Handrail and kerb

In progress

Kerb completed. 80% of handrail completed in both spans

4

Expansion joint

In progress

 

5

Wearing coat

Not started

 

6

Painting works

Not started

 

7

Stair case work

In Progress

Footing completed on Divine side. Columns reached up to EGL

 