Weekly Progress of Adjacent span of Divine Nagar ROB as on 26.08.15
|
Sl. No:
|
Particulars
|
Status
|
Remarks
|
1
|
Slab RP1-P6A ADJACENT SPAN
|
Completed
|
Slab completed
|
2
|
Slab RP2-P7 ADJACENT SPAN
|
In progress
|
Slab completed
|
3
|
Handrail and kerb
|
In progress
|
Kerb completed. 80% of handrail completed in both spans
|
4
|
Expansion joint
|
In progress
|
|
5
|
Wearing coat
|
Not started
|
|
6
|
Painting works
|
Not started
|
|
7
|
Stair case work
|
In Progress
|
Footing completed on Divine side. Columns reached up to EGL
|