   weekly progress as on 4.1.2011
    

 

 

SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week-1 Balance  work-2 Cumulative delay in weeks afterSpplagmnt  Work  planned  during the week-4 Actual work done during the last week-5 Short fall in the last week -6 Work   Planned for next week  Remarks 
1 Re wall towards NH side  100% 0 100 19 0 0 0 0   
2 RE wall towards Pulikkakadavuside  100% 99 2 39 1 1 1   
3 Approach Span  5 No  4 1 28   
4 Railway span  3No  0 0 26               
5 Pile (Rly)pulikakadavu side  9 4 5 46  0  0 0  0  Caution from railways awaited. Boring is not  possible at the P8 location. 
6 Pile (Rly)NH side  9 1 8   2 0 2 1 Machinery  Problem
7 Piers (Rly)  4No  0 0 35               
8 Handrail  (in the pulikkakadavu side)  426m  265 161     55  55  -   50   
9 Kerb  639m  360 279  70   60  10  50     

 

DATE 29/1/2011  31-01-2011  1/2/2011 2/2/2011 3/2/2011 4/2/2011
Weather  Sunny  Pleasant   Sunny     Sunny   Sunny  Sunny 
Labour 39 37 39 40 38 35 
 
Back
 
    
WORK OF RE WALL ON NH SIDE 1.2.2011

    
    
WORK OF KERB IN PULIKAKADAVU SIDE 2.2.2011

    
    
WORK OF HAND RAIL PORTION 1.2.2011

    
    
WORK OF HANDRAIL IS IN PROGRESS 4.2.2011

    
 
    
PILE BORING ON NH SIDE 2.2.2011

    
    
PILE AT P2 AFTER THE EXCAVATION 3.2.2011

    
    
EXCAVATION FOR PILING AT P8 31.1.2011

    
 
    
BORING AT PILE P7 ON NH SIDE 4.2.2011

      
 

 

 

 

 

 

 

 