   Progress Report of Kunhippally ROB as on 13.08.15
    

Progress Report of Kunhippally ROB as on 13.08.15

Sl. No

Activity Description

Total Quantity

Cumulative progress up to last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE MONTHAL BRIDGE SIDE

33

33

0

9

0

0

9

0

Completed

2

PILE NH SIDE

27

27

0

2

0

0

2

0

Completed

3

PILE LOAD TEST

1

1

0

COMPLETE

PILE LOAD TEST COMPLETE AT P15-1 LOCATION.

 

4

PILE CAP MONTHAL BRIDGE SIDE

9

9

0

3

0

0

1

0

Completed

5

PILE CAP  NH SIDE

7

7

0

1

0

0

3

0

Completed

6

PIER MONTHAL BRIDGE SIDE

9

9

0

4

0

0

0

0

Completed

7

PIER NH SIDE

7

7

0

 

0

0

 

0

Completed

8

PIER CAP MONTHAL BRIDGE  SIDE

9

9

0

1

0

0

2

 

Completed

9

PIER CAP NH SIDE

7

7

0

 

0

0

1

0

Completed

10

RC WALL MONTHAL BRIDGE  SIDE

100%

100%

0%

10%

0%

0%

10%

0%

Completed 

11

RC  WALL NH SIDE

100%

0%

100%

 

 3%

 3%

 

3% 

 

12

GIRDER MONTHAL BRIDGE SIDE

9

9

0

3

0

0

3

0

Completed 

13

GIRDER NH SIDE

7

6

1

3

0

0

3

0

 

14

DECK SLAB MONTHAL BRIDGE SIDE

9

9

0

0

0

0

1

0

Adjacent span

15

DECK SLAB NH SIDE

7

6

1

2

0

0

2

0

 

16

EXPANSION JOINT MONTHAL BRIDGE SIDE

9

7

2

 

1

1

 

0

 

17

EXPANSION JOINT NH SIDE

7

5

2

 

0

0

 

0

 

18

KERB  MONTHAL BRIDGE  SIDE

9

7

2

 

0

0

 

0

 

19

KERB NH SIDE

7

6

1

 

0

0

 

0

 

20

HANDRAIL MONTHAL BRIDGE SIDE

9

7

2

2

1

1

2

1

 

21

HANDRAIL NH SIDE

7

6

1

 

 0

0

 

 0

 

22

Painting

100%

45%

55%

 5%

5%

5%

 

2%

 

23

ROAD WORK

100%

5%

95.00%

 

0%

0%

10%

0%

 

24

BM/BC

100%

0%

100.00%

 

 

 

 

 

 

25

Others/Miscellaneous

 

0

0

 

 

 

 

 

 

26

Drainage + Culvert Monthal Side

100%

100%

0

 

0

0

40.00%

 Completed

 

 

 

 

 

 

 

 

 

 

 

27

RAILWAY PORTION

 

 

 

 

 

 

 

 

 

 

 

 

 
Back
 
    
RETAINING WALL CONCRETE IP @ NH SIDE

    
    
MONTHAL SIDE SERVICE ROAD IP

    
    
RCC RAFT CONCRETE IP @ NH SIDE

    
    
RAFT CONCRETE FOR RCC RETAINING WALL @ NH SIDE

    
 
    
NH SIDE RCC RETAINING WALL SHUTTERING

    
    
PAINTING IP @ MONTHAL SIDE

    
    
EXP JT. @ A2

    
 
    
EXP JT. A1 CONCRETE

      
 

 

 

 

 

 

 

 

Untitled Document