   Weekly progress of_ROB at Aloor Mala as on 13.08.2015
    

Weekly progress of ROB at Aloor-Mala Road as on 13.08.2015

All superstructure works except the work of expansion joints between adjacent spans and railway span are completed. Road furniture completed. Painting work in progress.  

 
Back
 
    
RAIL WAY SPAN

    
    
JCB TO BE REMOVED FOR TOLL BOOTH WORK

    
    
MALA SIDE

    
    
SERVICE ROAD MALA RHS

    
 
    
MAL SIDE OF ROB

    
    
ALOOR SIDE

    
    
ALOOR SIDE OF ROB

    
 
 
 

 

 

 

 

 

 

 