   Progress report of Divine Nagar ROB as on 07.08.15
    

Weekly Progress of Adjacent span of Divine Nagar ROB as on 07.08.15

Sl. No:

Particulars

Status

Remarks

1

Slab RP1-P6A ADJACENT SPAN

Completed

Slab completed

2

Slab RP2-P7 ADJACENT SPAN

 In progress

Concreting on 11.08.15

3

Handrail with kerb

In progress

Kerb completed in adjacent span RP1-P6A. Casting of horizontal railing members in progress

4

Expansion joint

Not started

 

5

Tarring work

Not started

 

6

Painting works

Not started

 

7

Stair case work

In Progress

Footing completed on Divine side. Columns reached up to EGL

 
Back
 
    