   Weekly report as on 04.02.2011
    


 

 

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

PILE SHORNUR  SIDE

9

9

0

0

0

0

0

0

PILE M.C SIDE

36

36

0

0

0

0

0

0

PILE CAP SHORNUR SIDE

3

3

0

0

0

0

0

0

PILE CAP  M.C SIDE

12

12

0

0

0

0

0

0

PIER SHORNUR  SIDE

3

3

0

0

0

0

0

0

PIER M.C SIDE

12

12

0

0

0

0

0

0

PIER CAP SHORNUR  SIDE

3

0

3

0

2

0

2

2

PIER CAP M.C SIDE

12

10

2

0

2

2

0

0

 
Back
 
    
PIER CAP P4 CONCRETING - 29.01.2011

    
    
CURING OF CONCRETE - 31.01.2011

    
    
STAGING AND SHUTTERING OF PIER CAP P3 - 01.02.2011

    
    
CONCRETING PIER CAP P3 - 02.02.2011

    
 
    
SHUTTERING FOR PIER CAP AP1 - 03.02.2011

    
    
COMPLETED PIER CAPS AT MEDICAL COLLEGE SIDE - 04.02.2011

      
 

 

 

 

 

 

 

 