Weekly Progress of Adjacent span of Divine Nagar ROB as on 31.07.15
|
Sl. No:
|
Particulars
|
Status
|
Remarks
|
1
|
Slab RP1-P6A ADJACENT SPAN
|
Completed
|
Slab completed
|
2
|
Slab RP2-P7 ADJACENT SPAN
|
In progress
|
Staging and shuttering completed
|
3
|
Handrail with kerb
|
In progress
|
Kerb completed in adjacent span RP1-P6A. Casting of hori. members of handrail in progress
|
4
|
Expansion joint
|
Not started
|
|
5
|
Tarring work
|
Not started
|
|
6
|
Painting works
|
Not started
|
|
7
|
Stair case work
|
In Progress
|
Footing completed on Divine side. Columns reached up to EGL
|