Weekly Progress of Eroor ROB as on 25.07.15
|
Sl. No
|
Activity Description
|
Total Quantity
|
Cumulative progress up to 25.07.15
|
Balance work up to 25.07.15
|
Actual work done during the week
|
Work planned for next week
|
Remarks
|
1
|
PILE Palarivattom side
|
19
|
19
|
0
|
0
|
0
|
A1-A,B,C / P1-A,B,C,D / P2-A,B,C,D / P3-A,B,C,D / P4-A,B,C,D
|
2
|
PILE Tripunithura side
|
19
|
19
|
0
|
2
|
0
|
P5-A,B,C,D / P6-A,B,C,D , P7- A,B,C,D, P8- A,B,C,D, A2C
|
3
|
PILE CAP Palarivattom side
|
5
|
5
|
0
|
0
|
0
|
A1,P1,P2,P3,P4
|
4
|
PILE CAP Tripunithura side
|
5
|
5
|
0
|
0
|
0
|
P5, P6, P7, P8, A2
|
5
|
PIER Palarivattom side
|
5
|
5
|
0
|
0
|
0
|
A1,P1,P2,P3,P4
|
6
|
PIER Tripunithura side
|
5
|
0
|
5
|
0
|
2
|
-
|
7
|
PIER CAP Palarivattom side
|
5
|
4
|
1
|
0
|
1
|
A1,P1,P2,P3
|
8
|
PIER CAP Tripunithura side
|
5
|
0
|
5
|
0
|
1
|
-
|
9
|
Slab Palarivattom side
|
4
|
2
|
2
|
0
|
1
|
P2 - P3, P1-P2
|
10
|
Slab Tripunithura side
|
4
|
0
|
4
|
0
|
0
|
-
|
11
|
Adjacent span Palarivattom side
|
1
|
0
|
1
|
0
|
0
|
-
|
12
|
Adjacent span Tripunithura side
|
1
|
0
|
1
|
0
|
0
|
-
|
13
|
Service road Palarivattom east
|
100%
|
0%
|
100%
|
0%
|
100%
|
-
|
14
|
Service road Palarivattom west
|
100%
|
0%
|
100%
|
0%
|
100%
|
-
|
15
|
Service road Tripunithura east
|
100%
|
0%
|
100%
|
0%
|
100%
|
-
|
16
|
Service road Tripunithura west
|
100%
|
0%
|
100%
|
0%
|
100%
|
-
|
|