   Progress Report of Kunhippally ROB as on 25.07.15
    

Progress Report of Kunhippally ROB as on 25.07.15

Sl. No

Activity Description

Total Quantity

Cumulative progress up to last week

Balance work up to last week

Cumulative delay in Qty up to last week

Work planned during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work Planned for next week

Remarks

1

PILE MONTHAL BRIDGE SIDE

33

33

0

9

0

0

9

0

Completed

2

PILE NH SIDE

27

27

0

2

0

0

2

0

Completed

3

PILE LOAD TEST

1

1

0

COMPLETE

PILE LOAD TEST COMPLETE AT P15-1 LOCATION.

 

4

PILE CAP MONTHAL BRIDGE SIDE

9

9

0

3

0

0

1

0

Completed

5

PILE CAP NH SIDE

7

7

0

1

0

0

3

0

Completed

6

PIER MONTHAL BRIDGE SIDE

9

9

0

4

0

0

0

0

Completed

7

PIER NH SIDE

7

7

0

 

0

0

 

0

Completed

8

PIER CAP MONTHAL BRIDGE SIDE

9

9

0

1

0

0

2

 

Completed

9

PIER CAP NH SIDE

7

7

0

 

0

0

1

0

Completed

10

RC WALL MONTHAL BRIDGE SIDE

100%

100%

0%

10%

0%

0%

10%

0%

Completed 

11

RC WALL NH SIDE

100%

0%

1

 

 

 

 

 

 

12

GIRDER MONTHAL BRIDGE SIDE

9

9

0

3

0

0

3

0

Completed 

13

GIRDER NH SIDE

7

6

1

3

0

0

3

0

 

14

DECK SLAB MONTHAL BRIDGE SIDE

9

8

1

0

0

0

1

1

Adjacent span

15

DECK SLAB NH SIDE

7

6

1

2

0

0

2

0

 

16

EXPANSION JOINT MONTHAL BRIDGE SIDE

9

7

2

 

0

0

 

0

 

17

EXPANSION JOINT NH SIDE

7

5

2

 

0

0

 

0

 

18

KERB MONTHAL BRIDGE SIDE

9

7

2

 

0

0

 

0

 

19

KERB NH SIDE

7

5

2

 

0

0

 

0

 

20

HANDRAIL MONTHAL BRIDGE SIDE

9

7

2

2

0

0

2

0

 

21

HANDRAIL NH SIDE

7

4

3

 

 1

0

 

 1

 

22

Painting

100%

35%

65%

 

5%

5%

5% 

5%

 

23

ROAD WORK

100%

5%

95.00%

 

0%

0%

10%

0%

 

24

BM/BC

100%

0%

100.00%

 

 

 

 

 

 

25

Others/Miscellaneous

 

0

0

 

 

 

 

 

 

26

Drainage + Culvert Monthal Side

100.00%

100%

5 %

 

5%

5%

40.00%

0% 

 Completed

 

 

 

 

 

 

 

 

 

 

 

27

RAILWAY PORTION

 

 

 

 

 

 

 

 

 

 

 

 

 
Back
 
    
VIEW FROM MONTHAL SIDE

    
    
VIEW FROM MONTHAL SIDE ABUTMENT

    
    
MONTHAL ADJACENT SLAB WRKS IP

    
    
SLAB CONCRETE

    
 
    
ADACENT SLAB MONTHAL SIDE CONCRETE

    
    
CONCRETE OR SLAB P8-P9

      
 

 

 

 

 

 

 

 