   Progress Report of Aloor Mala ROB as on 25.07.15
    

PROGRESS OF ROB ALOOR-MALA ROB AS ON 25-07-2015.

 

 Sl. No:

Description

Completed/ In Progress

Remarks

1

Piling

Completed.

Completed 32/32

2

Pile cap

Completed.

COMPLETED 8OUT OF 8

3

Pier

Completed.

Completed 6out of 6.

4

Pier cap

Completed.

6 nos completed out of 6.

5

Girder

Completed

6 completed OUT OF 6

6

Slab

Completed

6 completed out of 6.

7

Handrail with kerb

Completed

Kerb 6 nos completed out of 6, Handrail 6 out of 6 completed.

8

Expansion joint

Completed

6 OUT OF 6

9

Tarring work

completed

Completed.

10

Diversion road

completed

Aloor right side 100% completed. Mala side LHS 100%

11

Retaining wall work up to wall top

completed

Completed 4 sides.

12

Load test.

Completed.

In P4 location.

13

Service road work

Completed.

All four sides are completed.

14

Earth filling inside the approaches

completed

Completed

15

Under pass work

completed

Completed

16

Retaining wall kerb and handrail work Aloor side.

completed

Aloor side 100% completed.

17

Retaining wall kerb and handrail work Mala side.

completed

Mala side 100 % completed.

18

Adjacent span P3 - RP2

completed

Girder and Slab, Handrail with kerb, Expansion joint completed

 

19

Adjacent span P2 - RP1

Completed

Girder and slab completed, Handrail with kerb, Expansion joint completed.

 

20

GSB work in approach road Aloor side

completed

Aloor side GSB completed

21

GSB work in approach road mala side

completed

Mala side completed.

22

WMM work in approach road ALOOR side

completed

Aloor side WMM completed

23

WMM work in approach road MALA side

completed

Mala side WMM completed.

24

DBM,BC works

completed

Works completed.

25

Painting

In progress

Aloor side slab bottom completed. Mala side in progress. First coat painting of Handrails completed

26

CC Wearing coat on adjacent spans

Completed

Both spans completed

27

Expansion joint to adjacent spans

Completed

Both spans completed

 
Back
 
    
MALA SIDE

    
    
SERVICE ROAD MALA SIDE LHS

    
    
RAILWAY SPAN WORKS IN PROGRESS

    
    
ALOOR SIDE OF ROB

    
 
    
ADJ_SPAN RP1-P2

    
    
PAINTING WORK IN PROGRESS

      
 

 

 

 

 

 

 

 