Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886930
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Progress_Report_of_Eroor_ROB_as_on_17.07.15
    

Weekly Progress of Eroor ROB as on 17.07.15

Sl. No

Activity Description

Total Quantity

Cumulative progress up to 17.07.15

Balance work up to 17.07.15

Actual work done during the week

Work planned for next week

Remarks

1

PILE Palarivattom side

19

19

0

0

0

A1-A,B,C / P1-A,B,C,D / P2-A,B,C,D / P3-A,B,C,D / P4-A,B,C,D

2

PILE Tripunithura side

19

19

0

2

0

P5-A,B,C,D / P6-A,B,C,D , P7- A,B,C,D, P8- A,B,C,D, A2C

3

PILE CAP Palarivattom side

5

5

0

0

0

A1,P1,P2,P3,P4

4

PILE CAP Tripunithura side

5

5

0

0

0

P5, P6, P7, P8, A2

 

5

PIER Palarivattom side

5

5

0

0

0

A1,P1,P2,P3,P4

6

PIER Tripunithura side

5

0

5

0

2

-

7

PIER CAP Palarivattom side

5

4

1

0

0

A1,P1,P2,P3

8

PIER CAP Tripunithura side

5

0

5

0

0

-

9

Slab Palarivattom side

4

2

2

0

0

P2 - P3, P1-P2

 

10

Slab Tripunithura side

4

0

4

0

0

-

11

Adjacent span Palarivattom side

1

0

1

0

0

-

12

Adjacent span Tripunithura side

1

0

1

0

0

-

13

Service road Palarivattom east

100%

0%

100%

0%

100%

-

14

Service road Palarivattom west

100%

0%

100%

0%

100%

-

15

Service road Tripunithura east

100%

0%

100%

0%

100%

-

16

Service road Tripunithura west

100%

0%

100%

0%

100%

-

 
Back

No images are uploaded for this Weekly Reports

 
 
 

 

 

 

 

 

 

 

Untitled Document