Weekly Progress of Adjacent span of Divine Nagar ROB as on 17.07.15
Sl. No:
Particulars
Status
Remarks
1
Slab RP1-P6A ADJACENT SPAN
Completed
Slab completed
2
Slab RP2-P7 ADJACENT SPAN
In progress
Staging work started
3
Handrail with kerb
Kerb completed in adjacent span RP1-P6A
4
Expansion joint
Not started
5
Tarring work
6
Painting works
7
Stair case work
In Progress
Footing completed on Divine side. Columns reached up to EGL