   Progress_report_of_Divine_Nagar_ROB_as_on_17.07.15
    

Weekly Progress of Adjacent span of Divine Nagar ROB as on 17.07.15

Sl. No:

Particulars

Status

Remarks

1

Slab RP1-P6A ADJACENT SPAN

Completed

Slab completed

2

Slab RP2-P7 ADJACENT SPAN

In progress

Staging work started

3

Handrail with kerb

In progress

Kerb completed in adjacent span RP1-P6A

4

Expansion joint

Not started

 

5

Tarring work

Not started

 

6

Painting works

Not started

 

7

Stair case work

In Progress

Footing completed on Divine side. Columns reached up to EGL

 
Back
 
    
STAGING WORK STARTED IN RP2-P7.

    
    
HANDRAIL REINFORCEMENT WORK

    
    
FOOTING FOR STAIRCASE COLUMN.

    
    
DIVINE SIDE OF ROB.

    
 
    
RAILWAY SPAN CRASH BARRIER

      
 

 

 

 

 

 

 

 