   Progress Report of Angadippuram ROB as on 04.07.15
    

Progress Report For ROB Angadippuram for the week ending on 04-07-2015

 

Sl. No

Activity Description

Total Quantity

Cumulative progress up to last week

Balance work up to last week

Cumulative delay in Qty up to last week

Work planned during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work Planned for next week

No of days remaining for completion as per the weekly plan

1

Pile

56

56

0

0

0

0

0

0

 

2

Pile cap

18

13

5

0

0

0

0

0

 

3

Pier

16

11

7

0

0

0

0

0

 

4

Pier cap

16

9

7

0

0

0

0

0

 

5

Girders

54

3

51

0

0

0

0

0

 

6

Deck slab

18

0

18

0

0

0

0

0

 

50% of Retaining Wall and 12% of drainage completed. 

 
Back
 
    
EARTH WORK-SERVICE ROAD-PERINTHALMANNA SIDE

    
    
SERVICE ROAD WORK-PERINTHALMANNA SIDE

    
    
EARTH WORK FOR DRAIN-ANGADIPURAM SIDE

    
    
SERVICE ROAD WORK-ANGADIPURAM SIDE

    
 
    
RETAINING WALL WORK-ANGADIPURAM SIDE

    
    
DRAIN WORK -ANGADIPURAM SIDE

      
 

 

 

 

 

 

 

 

Untitled Document