Progress Report For ROB Angadippuram for the week ending on 27-06-2015
Sl. No
Activity Description
Total Quantity
Cumulative progress up to last week
Balance work up to last week
Cumulative delay in Qty up to last week
Work planned during the week
Actual work done during the week
Cumulative delay in Qty up to this week
Work Planned for next week
No of days remaining for completion as per the weekly plan
1
Pile
56
0
2
Pile cap
18
13
5
3
Pier
16
11
7
4
Pier cap
9
Girders
54
51
6
Deck slab
45% of Retaining Wall and 40m drain completed on Angadipuram side.