   Weekly Progress Report as on 19.06.15
    

Progress Report of Kunjipally ROB as on 19.06.15

Sl. No

Activity Description

Total Quantity

Cumulative progress up to last week

Balance work up to last week

Cumulative delay in Qty up to last week

Work planned during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work Planned for next week

Remarks

1

PILE MONTHAL BRIDGE SIDE

33

33

0

9

0

0

9

0

Completed

2

PILE NH SIDE

27

27

0

2

0

0

2

0

Completed

3

PILE LOAD TEST

1

1

0

COMPLETE

PILE LOAD TEST COMPLETE AT P15-1 LOCATION.

 

4

PILE CAP MONTHAL BRIDGE SIDE

9

9

0

3

0

0

1

0

Completed

5

PILE CAP NH SIDE

7

7

0

1

0

0

3

0

Completed

6

PIER MONTHAL BRIDGE SIDE

9

9

0

4

0

0

0

0

Completed

7

PIER NH SIDE

7

7

0

 

0

0

 

0

Completed

8

PIER CAP MONTHAL BRIDGE SIDE

9

9

0

1

0

0

2

 

Completed

9

PIER CAP NH SIDE

7

7

0

 

0

0

1

0

Completed

10

RC WALL MONTHAL BRIDGE SIDE

100%

90%

10%

10%

10%

10%

10%

10%

 

11

RC WALL NH SIDE

100%

0%

1

 

 

 

 

 

 

12

GIRDER MONTHAL BRIDGE SIDE

9

8

1

3

0

0

3

0

 

13

GIRDER NH SIDE

7

6

1

3

0

0

3

0

 

14

DECK SLAB MONTHAL BRIDGE SIDE

9

8

1

0

1

1

1

0

p9-p10 done

15

DECK SLAB NH SIDE

7

6

1

2

0

0

2

0

 

16

EXPANSION JOINT MONTHAL BRIDGE SIDE

9

3

6

 

1

1

 

0

 

17

EXPANSION JOINT NH SIDE

7

5

2

 

2

2

 

0

 

18

KERB MONTHAL BRIDGE SIDE

9

7

2

 

0

0

 

0

 

19

KERB NH SIDE

7

5

2

 

0

0

 

0

 

20

HANDRAIL MONTHAL BRIDGE SIDE

9

6

3

2

2

1

2

0

 

21

HANDRAIL NH SIDE

7

1

6

 

 1

 

 1

 

22

Painting

100%

25%

75%

 

5%

5%

 

5%

 

23

ROAD WORK

100%

5%

95.00%

 

0%

0%

10%

0%

 

24

BM/BC

100%

0%

100.00%

 

 

 

 

 

 

25

Others/Miscellaneous

 

0

0

 

 

 

 

 

 

26

Drainage + Culvert Monthal Side

100.00%

90.00%

10.00%

 

10.00%

0.00%

40.00%

 

 

 

 

 

 

 

 

 

 

 

 

 

27

RAILWAY PORTION

 

 

 

 

 

 

 

 

 

 

 

 

 
Back
 
    
IMG-20150618-WA0008

    
    
DIRT WALL @ A2 IP

    
    
DIVERTION ROAD FOR MONTHAL SIDE ADJACENT SPAN

    
    
DIVERTION ROAD PREPARATION

    
 
    
IMG-20150618-WA0006

    
    
PAINTING IP @ MONTHAL SIDE

    
    
PAINTING IP @ P13-P14

    
 
    
PAINTING WRKS IP

    
    
VIEW OF MONTHAL SIDE FROM RAILWAY PIER CAP

    
    
WP_20150619_12_25_44_PRO

    
 
 
 

 

 

 

 

 

 

 