   Weekly Progress as on 19-06-2015
    

Progress Report For ROB Angadippuram for the week ending on 19-06-2015

 

Sl. No

Activity Description

Total Quantity

Cumulative progress up to last week

Balance work up to last week

Cumulative delay in Qty up to last week

Work planned during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work Planned for next week

No of days remaining for completion as per the weekly plan

1

Pile

56

56

0

0

0

0

0

0

 

2

Pile cap

18

13

5

0

0

0

0

0

 

3

Pier

18

11

7

0

0

0

0

0

 

4

Pier cap

16

8

8

0

1

1

0

0

 

5

Girders

54

3

51

0

0

0

0

0

 

6

Deck slab

18

0

18

0

0

0

0

0

 

7

Retaining wall

100%

5%

100%

0

15%

5%

10%

20%

6

8

Drain

100%

0

100%

0

0

0

0

5%

6

 
Back
 
    
STAGING WORK AT P15-P16

    
    
ROAD PATCH WORK

    
    
RETAINING WALL FOUNDATION -ANGADIPURAM SIDE

    
    
GIRDER P3-P4

    
 
    
EARTH WORK EXCAVATION OF RETAINING WALL-ANGADIPURAM SIDE

    
    
DRAIN WORK- ANGADIPURAM SIDE (2)

    
    
DRAIN CONCRETE- ANGADIPURAM SIDE

    
 
    
BUILDING DISMANTLING- ANGADIPURAM SIDE NEAR RAILWAY GATE

      
 

 

 

 

 

 

 

 