Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888136
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress As On 19-06-2015.
    

PROGRESS OF ROB ALOOR-MALA ROB AS ON 19-06-2015.

 

 Sl. No:

Description

Completed/ Progress

Remarks

1

Piling

Completed.

Completed 32/32

2

Pile cap

Completed.

COMPLETED 8OUT OF 8

3

Pier

Completed.

Completed 6out of 6.

4

Pier cap

Completed.

6 nos completed out of 6.

5

Girder

Completed

6 completed OUT OF 6

6

Slab

Completed

6 completed out of 6.

7

Handrail with kerb

In progress

Kerb 6 nos completed out of 6, Handrail 6 out of 6 completed.

8

Expansion joint

In progress

6 OUT OF 6

9

Tarring work

completed

Completed.

10

Diversion road

completed

Aloor right side 100% completed. Mala side LHS 100%

11

Retaining wall work up to wall top

completed

Completed 4 sides.

12

Load test.

Completed.

In P4 location.

13

Service road work

Completed.

All four sides are completed.

14

Earth filling inside the approaches

completed

Completed

15

Under pass work

completed

Completed

16

Retaining wall kerb and handrail work Aloor side.

completed

Aloor side 100% completed.

17

Retaining wall kerb and handrail work Mala side.

completed

Mala side 100 % completed.

18

Adjacent span P3 - RP2

completed

Girder and Slab, Handrail with kerb, Expansion joint completed

19

Adjacent span P2 - RP1

In progress

Girder completed, Slab in progress.

20

GSB work in approach road Aloor side

completed

Aloor side GSB completed

21

GSB work in approach road mala side

completed

Mala side completed.

22

WMM work in approach road ALOOR side

completed

Aloor side WMM completed

23

WMM work in approach road MALA side

completed

Mala side WMM completed.

24

DBM,BC, works

completed

Works completed.

25

Painting

In progress

Aloor side slab bottom completed

 
Back
 
    
WEARING COAT STARTED IN RAILWAY SPAN

    
    
BOTTOM OF SLABS -PAINTING WORK

    
    
ALOOR SIDEF ROB.

    
    
ADJACENT SPAN COMPLETED IN RP1-P2.

    
 
 
 

 

 

 

 

 

 

 

Untitled Document