Prevoius Weekly Reports

   Weekly Progress as on 12.06.15
    

Progress Report For ROB Angadippuram for the week ending on  12-06-2015

 

Si No

Activity Description

Total Quantity

Cumulative progress up to last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaining  for completion as per the weekly plan

1

Pile

56

56

0

0

0

0

0

0

 

2

Pile cap

18

13

5

0

0

0

0

0

 

3

Pier

18

11

7

0

0

0

0

0

 

4

Pier cap

16

8

8

0

1

1

0

0

 

5

Girders

54

3

51

0

0

0

0

0

 

6

Deck slab

18

0

18

0

0

0

0

0

 

7

Retaining wall

100%

0

100%

0

5%

5%

0

15%

6

8

Drain

100%

0

100%

0

0

0

0

5%

6

 
Back
 
    
RETAINING WALL FOUNDATION WORK IN PROGRESS

    
    
RETAINING WALL FOUNDATION WORK IN PROGRESS (2)

    
    
PIERCAP P14- CONCRETING

    
    
GIRDER P3-P4

    
 
    
GIRDER P3-P4 (2)

    
    
BUILDING DISMANTLING- PERINTHALMANNA SIDE

    
    
EARTH WORK-RETAINING WALL FOUNDATION

    
 
 
 

 

 

 

 

 

 

 