Progress of Aloor Mala ROB as on 12.06.15
|
Sl. No:
|
Description
|
Completed/ Progress
|
Remarks
|
1
|
Piling
|
Completed.
|
Completed 32/32
|
2
|
Pile cap
|
Completed.
|
COMPLETED 8OUT OF 8
|
3
|
Pier
|
Completed.
|
Completed 6out of 6.
|
4
|
Pier cap
|
Completed.
|
6 nos completed out of 6.
|
5
|
Girder
|
Completed
|
6 completed OUT OF 6
|
6
|
Slab
|
Completed
|
6 completed out of 6.
|
7
|
Handrail with kerb
|
In progress
|
Kerb 6 nos completed out of 6, Handrail 6 out of 6 completed.
|
8
|
Expansion joint
|
In progress
|
6 OUT OF 6
|
9
|
Tarring work
|
completed
|
Completed.
|
10
|
Diversion road
|
completed
|
Aloor right side 100% completed. Mala side LHS 100%
|
11
|
Retaining wall work up to wall top
|
completed
|
Completed 4 sides.
|
12
|
Load test .
|
Completed.
|
In P4 location.
|
13
|
Service road work
|
Completed.
|
All four sides are completed.
|
14
|
Earth filling inside the approaches
|
completed
|
Completed
|
15
|
Under pass work
|
completed
|
Completed
|
16
|
Retaining wall kerb and handrail work Aloor side.
|
completed
|
Aloor side 100% completed.
|
17
|
Retaining wall kerb and handrail work Mala side.
|
completed
|
Mala side 100 % completed.
|
18
|
Adjacent span P3 - RP2
|
completed
|
Girder and Slab, Handrail with kerb, Expansion joint completed
|
19
|
Adjacent span P2 - RP1
|
In progress
|
Girder completed, Slab in progress.
|
20
|
GSB work in approach road Aloor side
|
completed
|
Aloor side GSB completed
|
21
|
GSB work in approach road mala side
|
completed
|
Mala side completed.
|
22
|
WMM work in approach road ALOOR side
|
completed
|
Aloor side WMM completed
|
23
|
WMM work in approach road MALA side
|
completed
|
Mala side WMM completed.
|
24
|
DBM,BC, works
|
completed
|
Works completed.
|