   Weekly Progress Report as on 12.06.15
    

The staging work for the casting of adjacent span at Kadukutty side is completed and placing of rebar in progress. The slab is expected to be casted during the next week.

 
Back
 
    
REINFORCEMENT WORK OF P6A-RP1 SPAN

    
    
SPAN RP1-P6A WORK IN PROGRESS

    
    
KADUKUTTY SIDE OF ROB

    
    
RAILWAY SPAN

    
 
 
 

 

 

 

 

 

 

 