   Weekly Progress Report as on 28/01/2011
    

 

Progress Report For Payyannur ROB for the week ending on 28-01-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE THRIKKARIPUR  SIDE

33

33

0

0

0

0

0

0

 

2

PILE EZHIMALA SIDE

27

21

6

3

3

6

0

0

 

3

PILE PAYYANNUR SIDE

27

25

2

2

2

2

0

0

 

4

PILE CAP THRIKKARIPUR  SIDE

11

8

3

2

2

0

2

2

 

5

PILE CAP EZHIMALA SIDE

9

3

6

1

2

0

2

3

 

6

PILE CAP PAYYANNUR SIDE

9

4

5

5

2

1

4

3

 

7

PIER THRIKKARIPUR  SIDE

11

7.5

3.5

0.5

0

0.5

0

0

 

8

PIER EZHIMALA SIDE

9

0

9

3

2

0

3

3

 

9

PIER PAYYANNUR SIDE

9

1

8

7

3

0

8

3

 

10

PIER CAP THRIKKARIPUR  SIDE

11

3

8

4

2

1

3

3

 

11

PIER CAP EZHIMALA SIDE

9

0

9

1

1

0

1

2

 

12

PIER CAP PAYYANNUR SIDE

9

0

9

5

2

0

5

3

 

 
Back
 
    
STAGING WORK OF APPROACH SLAB (28/01/2011)

    
    
PILE P15 (28/01/2011)

    
    
BORING OF PILE P14 B (28/01/2011)

    
    
PIERS P4,P5,P7 & P8 (28/01/2011)

    
 
    
P3 PIER CAP (28/01/2011)

    
    
P1, P2 PIER CAPS (28/01/2011)

      
 

 

 

 

 

 

 

 