Prevoius Weekly Reports

   weekly progress 28.1.2011
    

 

SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week(1) Balance  work(2) Cumulative delay in weeks afterSpplagmnt (3) Work  planned  during the week(4) Actual work done during the last week(6) Short fall in the last week (7) Work   Planned for next week (8) Remarks 
1 Re wall towards NH side  100% 1 99 0 0 0 0   
2 RE wall towards Pulikkakadavuside  100% 99 2 38 1 1 1   
3 Approach  5 No  4 1 27   
 Span 
4 Railway  3No  0 0 25               
 span 
5 Pile (Rly)pulikakadavu side  9 3 6 45  2  1   1    1    
  
6 Pile (Rly)Nh side  9 1 8   2 1 1 1  
6 Piers (Rly)  4No  0 0 35               
7 Handrail  (in the pulikkakadavu side)    426m  273 153     55  56  -   60    
8 Kerb  639m  338 303  70   70     70    
9 Road work  100% 0 0                  
10 Friction slab towards Pulikkakadavu side  128m  128      0 10 0 0     
11 Approachslab  2 No  1                     
12 Cap Beam  128m  128             0  0    
  date 22.1.2011 24.1.2011 25.1.2011 27.1.2011 28.1.2011          
No of Labours 35 40 40 41 39          
Climate Sunny Sunny Sunny Sunny  Sunny          

 

 
Back
 
    
PILE BORING WORK FOR PIER P1 ON NH SIDE 22.1.2011

    
    
PILE BORING FOR PIER P2 ON PULIKKAKDAVI SIDE 24.1.2011

    
    
WORK OF FRICTION SLAB 25.1.2011

    
    
WORK OF RE WALL ON NH SIDE 27.1.2011

    
 
    
PILE BORING FOR PIER P2 ON PULIKKAKDAVI SIDE 28.1.2011

    
    
HAND RAIL PORTION COMPLETED 28.1.2011

      
 

 

 

 

 

 

 

 